Generator Specification Checklist for EPC Projects

Table of Contents

EPC generator specification checklist showing RFQ sections for project intent, electrical fundamentals, load profile and motor starting, duty rating (ESP/PRP/COP), ATS/load shedding/paralleling controls, site derating, packaging, switchgear boundaries, and FAT/SAT deliverables.
Use this Enerzip EPC RFQ checklist to align suppliers on the “moment of truth” events (ATS transfer, staged load pick-up, largest motor start, UPS behavior, thermal run), define controls scope and site derating inputs, and require FAT/SAT evidence so quotes are comparable and disputes are reduced.

Reviewed by: Enerzip Power Technology (Weifang) Co., Ltd. – Applications & Integration Team
Last updated: 2026-02-02
Update policy: This checklist is reviewed when common EPC control scopes (ATS/paralleling), fuel compliance expectations, or typical acceptance testing practices (FAT/SAT) change.
Scope: RFQ-ready specification checklist for industrial generator systems (diesel / natural gas / biogas), focusing on duty cycle definition, control scope clarity, and site-condition translation.

How to use: Treat this as a “supplier alignment tool.” If you complete the key sections and ask vendors to respond with a compliance matrix, you dramatically reduce scope gaps, commissioning surprises, and post-delivery disputes.

Note: Rating definitions and interpretations can vary across manufacturers and markets. Always confirm the exact rating basis in the supplier’s datasheet and the agreed FAT/SAT test scope.

About the Reviewing Team

Enerzip Applications & Integration Team supports EPC contractors, distributors, and industrial users by translating load profiles, duty cycles,
and site constraints into actionable generator configurations. We typically validate assumptions through FAT/SAT planning, staged load pick-up logic,
and site airflow/cooling checks—because most project failures happen at transfer, motor start, or high-ambient operation.

Why EPC Generator RFQs Fail (and How to Fix Them)

Most EPC generator RFQs don’t fail because teams “forgot the kVA.” They fail because the RFQ does not define what must happen during the critical moments:
utility transfer, staged load pick-up, largest motor starts, and high-ambient operation. When those moments are undefined, suppliers guess—and the project pays later.

Common RFQ outcomes when scope is unclear

  • Everyone quotes a different size because the load pick-up strategy is not defined.
  • Cooling is underestimated because ambient and enclosure airflow path are missing.
  • ATS timing and re-acceleration behavior are ignored until commissioning.
  • UPS/rectifier behavior is assumed, which creates step-load trips.
  • Noise limits are specified without distance/measurement method, causing disputes.

What a “project-grade” generator specification checklist does

  • Turns “backup power” into a measurable performance statement.
  • Defines control boundaries (ATS / load shedding / paralleling) so vendors quote the same scope.
  • Captures site constraints early (ambient, altitude, dust, enclosure pressure drop).
  • Links rating language to acceptance tests (FAT/SAT) so the contract is harder to misunderstand.

Enerzip Field Note (why disputes happen): In post-delivery disputes, the root cause is often not “insufficient kW,” but an undefined test condition. A supplier may pass steady-state load yet fail on site because ATS transfer timing, motor re-acceleration, or enclosure airflow was never specified.

Practical fix: Put acceptance targets in the RFQ (example: voltage dip ≤ 15% for ≤ 1–2 s during the worst motor start event for PLC-heavy sites) and link them to FAT/SAT scope.

How to Use This Checklist in an EPC Workflow

Recommended EPC usage

  • Concept / early budget: complete Sections A–F with “assumptions stated.”
  • Procurement RFQ: complete Sections A–I; request a compliance matrix from suppliers.
  • Pre-FAT: finalize acceptance targets, staged load pick-up plan, and documentation list.
  • Site commissioning: use the SAT checklist to validate transfer behavior, start sequence, and thermal margin.

How suppliers should respond

  • Return a line-by-line compliance table (Comply / Deviate / Optional / Not included).
  • State assumptions explicitly (ambient, altitude, fuel quality window, step-load behavior).
  • Attach datasheets and single-line drawings aligned with the stated control scope.

Specification Checklist (A–J)

Tip: The fastest way to make quotes comparable is to define (1) the “moment of truth” events, (2) staged load pick-up logic, and (3) site derating inputs.

A) Project definition & performance intent (the “why”)

A1. Facility / application

  • Industry: manufacturing / utility / water & wastewater / mining / telecom / hospital / data center / oil & gas
  • Operational goal: protect critical operations, reduce downtime risk, control total cost of ownership
  • Single site or multi-site rollout?

A2. Availability target

  • Architecture: single set / N+1 / 2N / parallel modular expansion
  • Downtime tolerance: acceptable outage duration
  • Maintenance strategy: can the site accept maintenance shutdowns?

A3. “Moment of truth” definition

  • Transfer type: open transition (break-before-make) or closed transition (make-before-break), if permitted by utility/interlocks
  • Expected transfer time and load pick-up sequence
  • Worst-case event: largest motor start after transfer? UPS step load? combined?

Enerzip Field Note (performance intent): RFQs that only specify “kVA rating” but do not define transfer behavior often procure the wrong solution.

Verification hook: Add an “event list” to the RFQ: (1) ATS transfer, (2) largest motor start, (3) UPS pick-up behavior, (4) thermal operation at design ambient.

B) Electrical fundamentals (the “what”)

B1. System voltage, frequency, and wiring

  • Rated voltage: e.g., 400/230V, 480/277V, 11kV (if HV project)
  • Frequency: 50Hz or 60Hz
  • Phase & wiring: 3P4W / 3P3W / 1P2W
  • Power factor basis for rating (commonly 0.8 unless specified otherwise)

B2. Grounding / earthing and neutral

  • Grounding system basis: TN-S / TT / IT / solidly grounded / resistance grounded (as applicable)
  • Neutral switching requirements at ATS (if required)
  • Earth fault protection philosophy

B3. Power quality expectations

  • Sensitive loads present? (PLC, VFD, medical devices, servers, instrumentation)
  • UPS type and behavior: step load vs ramp, input harmonics, generator compatibility notes
  • Voltage regulation expectation (define if needed; otherwise request supplier standard)

Note: Rating definitions and interpretations may vary by manufacturer and region; require vendors to state the rating basis and proposed test scope.

C) Load profile & motor starting (the “stress events”)

C1. Provide a load list with start method

Minimum load list fields:

  • Load tag / name; type (motor / VFD motor / UPS / lighting / heater / transformer / rectifier)
  • Quantity
  • Running kW and PF (or running kVA)
  • Starting method: DOL / star-delta / soft starter / VFD
  • Starting current or starting kVA (preferred from motor datasheet)
  • Duty: always-on / intermittent / emergency-only
  • Priority: must-run / delay-start / shedable

C2. Define the largest “single event”

  • Largest motor start (kW/HP, start method, acceleration time)
  • Largest step load (UPS/rectifier, HVAC group, process block)
  • Re-acceleration risk after transfer (motors that coast down and restart together)

C3. Staged start sequence (RFQ must include)

  • Essential controls & lighting first
  • Largest motor alone (if practical)
  • Secondary groups with time delays
  • Non-critical loads last

Enerzip Field Note (motor starts): If the RFQ does not state “largest motor start method,” vendors will assume differently and quotes become non-comparable.

Practical detail: Define an acceptable voltage dip target for the largest start event (example: ≤ 15% for ≤ 2 s for PLC-heavy sites) and confirm it during FAT/SAT.

D) Duty cycle & rating language (ESP/PRP/COP with careful wording)

D1. Define operating category in plain language

  • Emergency standby only (rare outages) vs frequent backup (weak grid) vs continuous/baseload
  • Expected annual runtime hours and longest continuous run
  • Typical load level during runtime (e.g., 40–70% average, occasional peaks)

D2. Use rating terms carefully

  • Require supplier to state which rating category they are quoting (ESP/PRP/continuous-type or equivalent).
  • Require kVA and kW shown together under a stated PF basis.
  • Require site conditions for which rating is valid (ambient, altitude).
  • Require proposed FAT/SAT test scope for validation.

Important: ISO 8528 terminology is widely used, but rating definitions and interpretations may vary by manufacturer and region. Confirm with datasheet and test scope.

E) Controls scope: ATS, load shedding, synchronization, and parallel logic

E1. ATS scope (define exact interfaces)

  • ATS rating (A), poles, neutral switching requirement
  • Transfer type: open transition vs closed transition (if applicable)
  • Transfer delay, re-transfer delay, re-transfer inhibit (if needed)
  • Return-to-utility behavior (manual/auto, cooldown, unload)

E2. Load shedding logic (tiering)

  • Tier 1: must-run (safety, controls, critical operations)
  • Tier 2: delay-start (pumps, compressors, staged HVAC)
  • Tier 3: shedable (non-critical loads)
  • Shedding triggers: underfrequency, overload, manual priority selection

E3. Paralleling and synchronization (if required)

  • Parallel quantity now and future expansion plan
  • Synchronizing controller scope and power management functions
  • Load sharing strategy (kW/kVAr sharing where applicable)
  • Black start logic (if a plant microgrid is involved)

E4. Remote monitoring and communications

  • Protocols: Modbus (RTU/TCP), SNMP, dry contacts, Ethernet gateways
  • Alarm list and event history requirements
  • Remote start/stop permissions and cybersecurity constraints (if any)

Enerzip Field Note (controls prevent oversizing): If you define staged load pick-up and shedding tiers, you often reduce alternator oversizing and improve stability.

Verification hook: Ask suppliers to propose a start sequence schedule (time delays) and show how it meets your voltage/frequency dip targets during the largest event.

F) Site conditions & derating: ambient, altitude, enclosure, dust, fuel

F1. Ambient temperature and altitude

  • Design ambient: typical and peak (e.g., 40–50°C)
  • Altitude and barometric conditions (if highland site)
  • Expected temperature rise inside enclosure/container

F2. Installation environment

  • Indoor / outdoor / rooftop / container compound
  • Dust/sand, humidity, corrosion risk (coastal vs inland)
  • Rain, flooding risk, drainage requirements

F3. Enclosure airflow and cooling path

  • Airflow direction constraints (front-to-back vs side discharge)
  • Allowable pressure drop in ducting (if ducts are used)
  • Recirculation prevention requirements

F4. Fuel conditions (diesel / natural gas / biogas)

  • Fuel type and availability constraints
  • For gas/biogas: methane range, pressure range, contaminant limits as defined by project
  • Fuel storage scope (day tank / base tank / external tank) and autonomy hours

Enerzip Field Note (hot sites fail on airflow): In high-ambient regions, many issues come from airflow path and recirculation—not nameplate kVA.

Practical SAT record: Require recording of coolant temperature at stable load, radiator inlet/outlet air temperature, and enclosure internal temperature during a representative run.

G) Mechanical & packaging scope: canopy, container, skid, fuel system

G1. Configuration

  • Open skid / silent canopy / weatherproof canopy / containerized power house
  • Service access requirements (side doors, maintenance clearance)
  • Lift points, forklift pockets, base frame requirements

G2. Noise specification (make it measurable)

  • Target noise in dB(A)
  • Distance (e.g., 7 m) and measurement condition (free field vs reflective)
  • Operating load condition for measurement (e.g., 75% or 100%)

G3. Fuel system scope

  • Base tank size and autonomy hours
  • Day tank and transfer pump scope (if required)
  • Fuel filtration / water separator requirements (if applicable)

G4. Optional accessories that change project integration

  • Battery chargers, block heaters, space heaters for alternator/enclosure
  • Fire detection/suppression interface for containerized systems (if required)
  • External emergency stop stations

H) Switchgear, protection, and integration boundaries

H1. Breaker and protection requirements

  • Main breaker type: MCCB/ACB, ratings, trip settings philosophy
  • Protection functions: over/under V, over/under Hz, overload, short circuit coordination (project-dependent)
  • Earth fault protection philosophy and measurement method

H2. Switchboard / distribution boundary

  • Is the supplier providing only the genset, or also the LV switchboard?
  • Interlocks between ATS, generator breaker, and utility breaker
  • Metering: kW, kVA, kVAr, PF, kWh, event logs

H3. Cabling and terminations

  • Cable entry direction and gland plate requirements
  • Termination lugs and busbar expectations (project-dependent)
  • Grounding and bonding points on skid/container

I) Testing & documentation: FAT/SAT deliverables that prevent disputes

I1. FAT (Factory Acceptance Test) scope

  • Visual inspection, wiring check, labeling verification
  • Sensor and alarm function checks
  • Protection checks and emergency stop validation
  • Control logic: start/stop, cooldown, ATS interface (as applicable)
  • Load test (when required): staged load steps to evaluate dip and recovery

I2. SAT (Site Acceptance Test / commissioning) scope

  • Transfer test (utility-to-generator, generator-to-utility)
  • Start sequence validation (staged motors, delays, shedding)
  • Worst-case event test (largest motor start after transfer, UPS pick-up behavior)
  • Thermal verification at representative ambient and airflow conditions

I3. Documentation package (minimum)

  • Datasheets: engine, alternator, controller, ATS/switchgear (as supplied)
  • Single-line diagram (SLD)
  • Wiring diagrams and terminal schedules
  • GA drawings: dimensions, weight, lifting points, service clearance
  • Test reports: FAT results, insulation checks (if performed), load bank results (if performed)
  • O&M manuals and spare parts list

Enerzip Field Note (acceptance targets): Define acceptance targets in the RFQ and enforce them in FAT/SAT to reduce “it passed in factory but failed on site” risk.

Example targets (confirm per project): Voltage dip ≤ 15% for ≤ 1–2 s during worst motor start; frequency dip ≤ 10% with recovery within ≤ 5 s after largest step load.

J) Logistics, spares, warranty, and after-sales expectations

J1. Packaging and delivery

  • Delivery format: open skid / canopy / container
  • Seaworthy packing, anti-corrosion protection, shock indicators (if needed)
  • Shipping/customs documentation (as required)

J2. Commissioning support

  • Remote commissioning support or on-site support requirement
  • Training scope for operators and maintenance team

J3. Spares and consumables

  • Recommended spare parts list (one-year / two-year / critical spares)
  • Consumables list and maintenance interval assumptions

J4. Warranty statement (project-grade)

  • Warranty period and operating hour definition
  • Response expectations and escalation route
  • Clarify what is covered under system integration vs component warranty (as applicable)

Copy/Paste RFQ Template (Ready to Send)

Instruction: Copy the block below into your RFQ email or procurement document. Ask suppliers to respond with a compliance matrix and state all assumptions.

RFQ TITLE: Generator Specification Checklist (EPC Project)

1) Project overview

  • Facility/application:
  • Location / installation type (indoor/outdoor/container):
  • Availability target (single / N+1 / 2N / parallel expansion):
  • Duty cycle (annual hours, longest continuous run):
  • Critical “moment of truth” events to validate (ATS transfer, largest motor start, UPS pick-up, thermal run):

2) Electrical requirements

  • Voltage / frequency / phase / wiring:
  • Grounding / neutral requirements:
  • PF basis for rating:
  • Sensitive loads / UPS details (step vs ramp, harmonics, compatibility notes):

3) Load profile & motor starting

  • Provide load list with running kW/kVA, PF, start method (DOL/star-delta/soft starter/VFD), starting current/kVA, duty, priority
  • Largest motor details (kW/HP, start method, accel time)
  • Largest step load details (UPS/rectifier behavior)
  • Staged start sequence requirement (supplier to propose time delays)

4) Rating & duty statement (supplier must clarify)

  • Quoted rating category (ESP/PRP/continuous-type or equivalent)
  • kVA and kW stated together under PF basis
  • Validity conditions (ambient, altitude) and proposed derating assumptions
  • Proposed acceptance test scope aligned with project events

5) Controls scope

  • ATS scope (type, rating, poles, delays, neutral switching)
  • Load shedding tiers and logic (Tier 1/2/3)
  • Paralleling/synchronization scope (if applicable)
  • Remote monitoring protocols and alarm list

6) Site conditions

  • Design ambient and peak ambient
  • Altitude
  • Dust/sand/humidity/corrosion risks
  • Enclosure/container airflow constraints (ducting, pressure drop, recirculation avoidance)
  • Fuel type and constraints (diesel / natural gas / biogas; quality window if applicable)

7) Mechanical / packaging

  • Configuration: open / canopy / weatherproof / container
  • Noise requirement (dB(A), distance, test load)
  • Fuel storage and autonomy hours
  • Accessories (heaters, chargers, E-stop stations, etc.)

8) Switchgear and integration boundaries

  • Main breaker type and settings philosophy
  • Interlocks with utility and ATS
  • Switchboard scope boundary (by EPC or supplier)

9) Testing & deliverables

  • FAT scope (functional + protections + optional load bank steps)
  • SAT scope (transfer test, staged starts, worst-case event, thermal run)
  • Documentation package: SLD, wiring diagrams, GA, manuals, test reports, spares list

10) Supplier response format

  • Compliance matrix (Comply / Deviate / Optional / Not included)
  • Statement of assumptions and exclusions
  • Datasheets + drawings attached

Annexes

Annex A — Load list headings (Excel)

Field Example / Notes
Load Tag / Name P-101 Process Pump
Type Motor / VFD Motor / UPS / Lighting / Heater / Other
Qty 1 / 2 / 3…
Voltage / Phase / Frequency 400V / 3P / 50Hz
Running kW / PF / Running kVA kVA can be calculated if PF known
Running current (A) If available
Start method DOL / Star-Delta / Soft Starter / VFD
Starting current or Starting kVA Prefer motor datasheet
Start duration (s) Acceleration time
Duty Always / Intermittent / Emergency-only
Priority Must-run / Delay-start / Shedable
Notes Re-acceleration, harmonics, special constraints

Annex B — Acceptance targets (example)

  • Voltage dip: ≤ 15% for ≤ 1–2 seconds during worst start event (confirm with PLC/UPS tolerance)
  • Frequency dip: ≤ 10% with recovery within ≤ 5 seconds after largest step load
  • Thermal: coolant temperature stable within acceptable range at representative ambient and airflow conditions
  • ATS: transfer logic and staged restart behave as specified (no “all motors restart together”)

Annex C — Drawing / document list (minimum)

  • SLD (single-line diagram)
  • GA drawings (dimensions, weight, lifting points, service clearance)
  • Wiring diagrams + terminal schedules
  • Controller I/O list (if project requires)
  • FAT report + SAT checklist
  • O&M manuals + spare parts list

FAQ

1) Why do EPC quotes vary so much for the same “kVA” requirement?

Because the RFQ usually does not define the load pick-up strategy, ATS behavior, motor start method, and site derating conditions.
Suppliers apply different assumptions, producing different kVA and different scope.

2) Do I need to specify acceptance targets like voltage dip and frequency recovery?

If your site has PLC/VFD/UPS loads or large motor starts, yes. It makes quotes comparable and gives a measurable commissioning goal.
Targets must match the actual tolerance of your equipment.

3) Should the RFQ include FAT/SAT requirements?

Yes. Linking rating language to FAT/SAT scope reduces disputes and increases reliability.
A “pass” should mean the system passed the events that matter (transfer, staged starts, thermal run), not only steady load.

4) How do I avoid oversizing without risking trips?

Define staged starts, shedding tiers, ATS timing, and worst-case event tests. Many projects can reduce size and improve stability with better controls rather than larger nameplate.

Next Step

If you share (1) your load list (Excel), (2) site ambient/altitude, (3) duty cycle intent, and (4) ATS/control scope, Enerzip can turn this checklist into a project-ready RFQ package
and a supplier comparison matrix—so you can procure a reliable standby generator system with fewer surprises.

Note: This checklist is an engineering workflow guide. Final requirements should be confirmed against local codes, site drawings, equipment tolerances, and the agreed FAT/SAT test scope.

Related Products
Enerzip® Paralleling & Grid-connect Systems control panel for generator synchronization, load sharing, and grid connection

Paralleling & Grid-connect Systems

Enerzip® ATSE Series – Automatic Transfer Switches for Generator ATS front panel for automatic dual power transfer control

Automatic Transfer Switches (ATS)

Enerzip® E Series – Biogas Generator Sets open frame genset for farm-scale biogas power and simple on-site maintenance.

E Series – Biogas Generator Sets

Enerzip® C Series – Biogas Generator Sets open frame generator for waste-to-energy projects and reliable biogas power generation.

C Series – Biogas Generator Sets

Enerzip® W Series – High Voltage Generators open frame HV genset with direct 3.3–13.8kV output for industrial MV power

W Series – High Voltage Generators

Enerzip® Y Series – High Voltage Generators open frame HV genset with direct 3.3–13.8kV output for heavy-duty industrial power

Y Series – High Voltage Generators

Enerzip® MS Series – High Voltage Generators open frame HV genset with direct 3.3–13.8kV output for industrial MV power

MS Series – High Voltage Generators

Enerzip® M Series – High Voltage Generators open frame HV genset with direct 3.3–13.8kV output for industrial power systems

M Series – High Voltage Generators

Related News